Coordinated Work: Execution Programme and Research Delivery

A research programme on organizational needs, competencies, shared resources and decisions that improve the whole work system.

Research proposal. Work packages, possible papers and hypotheses describe planned work; they do not establish task registration, assignments or validated organizational effects.

The programme is shown in full in the selected language. Russian and Simplified Chinese remain author-prepared translations awaiting a separate fidelity review.

Prepared 18 November 2026. Status: source proposal for reconciliation and review. Muneral remains the authority for actual task identities, assignments, dependencies and execution states.

This programme has 23 epics, 104 work packages and 247 output-consuming blocking edges. It preserves all 72 original steps, adds 32 explicit missing work packages, and maps 16 potential papers and 12 hypotheses. The machine-readable graph and complete task contracts are the source for registration. The Russian programme and Simplified Chinese programme present the same scope tables and bind their source to this English text.

The 104 entries are work packages. Broad review batches, benchmark families and publication templates must be split into bounded children before dispatch. A proposed owner is not an actual assignment. The 128 programme/epic/package objects prepared for reconciliation are not 128 created Muneral objects.

Starting evidence and intended contribution

The initial research package retains 1,176 bibliographic records: 157 checked primary records and 1,019 citation candidates. Unique-work identity remains unresolved (26 title/year groups and four near-title pairs); completed full-text critical appraisals are zero. The retained revision-2 probe has 10 scenarios, 100 case-period observations and 190 elementary checks. These support a bounded numerical implementation claim, not agent effectiveness or validity for a real organization.

The proposed contribution is an organizational domain profile connecting needs, work networks, distinct resource semantics, competencies and decision evidence to Agent Situation and Context Assembly. Novelty must survive comparison with existing research; no new native KC artifact kind or execution authority follows from introducing a profile.

First epic: make the programme visible and actionable

CW-EP00 covers source freezing, the programme charter, this graph, EN/RU/zh-Hans Journal announcements, roadmap and repository navigation, native task reconciliation, verified public delivery and a bounded collective handoff. An accepted announcement may ship while native registration is pending; N08 requires both publication and registration receipts before the complete launch handoff closes.

Package Observable output Proposed accountable / executor Blocking inputs
CW-N01 — Freeze programme inputs and evidence boundary Source and evidence freeze manifest KC-Brain / KC-SWE Source inputs only
CW-N02 — Define programme charter and output families Programme charter and output inventory KC-Brain / KC-SWE CW-N01
CW-N03 — Build and validate execution graph Versioned execution programme and coverage validator KC-Brain / KC-SWE CW-N02
CW-N04 — Prepare EN/RU/zh-Hans announcement bundle Three-language announcement and research cards KC-Brain / KC-SWE CW-N02, CW-N03
CW-N05 — Publish repository and roadmap programme entries Repository and roadmap announcement integration KC-Brain / KC-SWE CW-N03, CW-N04
CW-N06 — Register and read back Muneral graph Muneral registration and exact readback ledger KC-Brain / KC-SWE CW-N03
CW-N07 — Deliver announcement and programme landing Published three-language launch receipt KC-Brain / KC-SWE CW-N04, CW-N05
CW-N08 — Complete collective handoff and first work batch Collective ownership and bounded first-batch handoff KC-Brain / KC-SWE CW-N06, CW-N07

Launch acceptance includes exact source and translation bindings, rights/attribution, independent review at the stated scope, hosted validation, an explicit rollback revision, publication workflow and anonymous served-page readback. Browser inspection must verify that the actual article is visible on desktop/mobile and that language switching preserves the issue; metadata or a lexical HTML check cannot establish those properties.

Parallel delivery sequence

The following diagram is an overview, not the authoritative 247-edge graph. Every real blocking edge in the JSON names the predecessor output it consumes.

Dependency diagram source
flowchart TD
  A["Freeze sources and programme"] --> B["Announce and reconcile tasks"]
  A --> C["Review sources and define claims"]
  C --> D["Models, schemas and study protocols"]
  D --> E["Manufacturing stand"]
  D --> F["Service stand"]
  D --> G["Project stand"]
  E --> H["Validated controlled comparisons"]
  F --> H
  G --> H
  H --> I["Eligible shadow use"]
  I --> J["Bounded field evaluation"]
  C --> K["Claim-specific scientific releases"]
  H --> K
  J --> K
  1. Launch and reconciliation. Freeze source/evidence, publish the truthful programme description, reconcile existing Muneral work and prepare the first bounded batch.
  2. Parallel foundations. Review primary sources, define needs/resources/work graphs, build the provenance schema, define rights and data contracts, and register study-specific questions.
  3. Parallel domain stands. Build manufacturing, service and project families after their own required inputs. Run independent oracles and model-validity checks before confirmatory comparison.
  4. Controlled evidence. Compare the current method, strong OR, no-retrieval agent, strong ordinary RAG and full KC profile under declared matched budgets; retain ablations, failures and uncertainty.
  5. Eligible real use. Bind an actual Arcanada task and implementation, collect shadow evidence, then evaluate a separately authorized bounded intervention and held-out transfer.
  6. Release by claim. A reviewed source map, a conditional proof and an organizational causal claim have different evidence obligations. A literature or formal result does not wait for a global field trial; a causal-effect claim still requires one or another justified identification design.

The dependency decisions retain the source edge history and justify each revision. The original dependency chain reaches 64 tasks; the proposed graph reaches 17. These are topological node counts, not days, effort estimates or demonstrated speedup. Capacity, review availability and duration estimates must be bound during native reconciliation. The existing six-role collective is reused; task rows do not create additional agents.

Epic register

Epic Scope Work packages Proposed accountable / executor
CW-EP00 Announcement and registration 8 KC-Brain / KC-SWE
CW-EP01 Corpus and research map 9 KC-Brain / Research-Arcana
CW-EP02 Needs and capability ontology 8 KC-Brain / Research-Arcana
CW-EP03 Organizational state and permitted sources 8 KC-Brain / KC-SWE
CW-EP04 Flows, capacity and constraints 8 KC-Brain / Research-Arcana
CW-EP05 Teams and capability planning 8 KC-Brain / Research-Arcana
CW-EP06 Forecasting, uncertainty and drift 7 KC-Brain / Research-Arcana
CW-EP07 Decision contracts and agent verification 8 Agent-Brain / Agent-SWE
CW-EP08 Experimental design and comparisons 5 KC-Brain / Research-Arcana
CW-EP09 Scientific publication in three languages 11 KC-Brain / KC-SWE
CW-EP10 Formal admissibility and resource types 3 KC-Brain / Research-Arcana
CW-EP11 Data rights, privacy and reference packages 2 KC-Brain / KC-SWE
CW-EP12 Independent oracles and model validity 2 KC-Brain / KC-SWE
CW-EP13 Manufacturing stand 1 KC-Brain / KC-SWE
CW-EP14 Service stand 1 KC-Brain / KC-SWE
CW-EP15 Project and knowledge-work stand 1 KC-Brain / KC-SWE
CW-EP16 Causality, observability and interference 3 KC-Brain / Research-Arcana
CW-EP17 Execution, concurrency and full cost 3 Agent-Brain / Agent-SWE
CW-EP18 Consumers and ecosystem integration 2 Agent-Brain / Agent-SWE
CW-EP19 Operator understanding and information value 1 KC-Brain / Research-Arcana
CW-EP20 Shadow, field and external reproduction 3 KC-Brain / Research-Arcana
CW-EP21 Dynamics and recursive feasibility 1 KC-Brain / Research-Arcana
CW-EP22 KC compatibility and evidence lineage 1 KC-Brain / KC-SWE

Complete work-package inventory

Every linked contract records numbered acceptance criteria, exact proposed output, evidence, negative control, source coverage, reviewer and consumed predecessor outputs.

Package Work Epic Blocking prerequisites
CW-N01 Freeze programme inputs and evidence boundary CW-EP00 None in this proposal
CW-N02 Define programme charter and output families CW-EP00 CW-N01
CW-N03 Build and validate execution graph CW-EP00 CW-N02
CW-N04 Prepare EN/RU/zh-Hans announcement bundle CW-EP00 CW-N02, CW-N03
CW-N05 Publish repository and roadmap programme entries CW-EP00 CW-N03, CW-N04
CW-N06 Register and read back Muneral graph CW-EP00 CW-N03
CW-N07 Deliver announcement and programme landing CW-EP00 CW-N04, CW-N05
CW-N08 Complete collective handoff and first work batch CW-EP00 CW-N06, CW-N07
CW-A01 Define review scope CW-EP01 CW-N01
CW-A02 Verify the seed bibliography CW-EP01 CW-A01
CW-A03 Extract citation candidates CW-EP01 CW-A01
CW-A04 Resolve publication identities CW-EP01 CW-A02, CW-A03
CW-A05 Expand field coverage CW-EP01 CW-A01
CW-A06 Screen full texts CW-EP01 CW-A02, CW-A04, CW-A05
CW-A07 Extract scoped claims CW-EP01 CW-A06
CW-A08 Review the scoping map CW-EP01 CW-A07
CW-N09 Frontload novelty discriminants CW-EP01 CW-A07
CW-B01 Define organizational units CW-EP02 CW-A01
CW-B02 Classify needs and situations CW-EP02 CW-B01
CW-B03 Map sectors and processes CW-EP02 CW-B01
CW-B04 Map occupations and competencies CW-EP02 CW-B01
CW-B05 Define resource semantics CW-EP02 CW-B01
CW-B06 Define performance measures CW-EP02 CW-B01
CW-B07 Assess annotation agreement CW-EP02 CW-B02, CW-B03, CW-B04, CW-B05, CW-B06
CW-B08 Evaluate held-out sectors CW-EP02 CW-B07
CW-C01 Build the typed work graph CW-EP03 CW-B01, CW-B02, CW-B05
CW-C02 Define event semantics CW-EP03 CW-C01
CW-C03 Separate demand observations CW-EP03 CW-C01, CW-B06
CW-C04 Represent availability calendars CW-EP03 CW-C01, CW-B04, CW-B05
CW-C05 Preserve provenance and conflicts CW-EP03 CW-C02, CW-A02, CW-N10
CW-C06 Specify freshness and invalidation CW-EP03 CW-C05
CW-C07 Prototype authorized adapters CW-EP03 CW-C02, CW-C03, CW-C04, CW-C05, CW-C06, CW-N15
CW-C08 Review the organization profile CW-EP03 CW-C07, CW-B08, CW-A08
CW-D01 Define flow conservation CW-EP04 CW-B05, CW-N14
CW-D02 Derive conditional throughput bounds CW-EP04 CW-D01
CW-D03 Model buffers and delays CW-EP04 CW-D01, CW-D02
CW-D04 Model setup and rework CW-EP04 CW-D01, CW-C03
CW-D05 Compare release policies CW-EP04 CW-D06, CW-N17
CW-D06 Add product mix and shared resources CW-EP04 CW-D03, CW-D04, CW-C04
CW-D07 Construct local-metric counterexamples CW-EP04 CW-D05, CW-B06
CW-D08 Review the flow model CW-EP04 CW-D07, CW-A08, CW-C08
CW-E01 Estimate task workload CW-EP05 CW-B04, CW-C03, CW-C04, CW-B06
CW-E02 Bind competency evidence CW-EP05 CW-B04
CW-E03 Optimize multiskill assignments CW-EP05 CW-E01, CW-E02, CW-D06
CW-E04 Model hiring lead times CW-EP05 CW-E01, CW-C04
CW-E05 Compare capacity alternatives CW-EP05 CW-E03, CW-E04, CW-F04, CW-N21
CW-E07 Constrain sustainable workload CW-EP05 CW-C04, CW-E03
CW-E08 Produce auditable role requirements CW-EP05 CW-E05, CW-E06, CW-E07, CW-A08, CW-C08
CW-N21 Model team complementarity and capability change CW-EP05 CW-E01, CW-E02, CW-C04
CW-F01 Reconcile hierarchical forecasts CW-EP06 CW-C03
CW-F02 Calibrate predictive uncertainty CW-EP06 CW-F01
CW-F03 Define external shock scenarios CW-EP06 CW-A02, CW-C01
CW-F04 Model decision delays CW-EP06 CW-C02, CW-C04
CW-F05 Optimize under uncertainty CW-EP06 CW-F02, CW-F03, CW-F04
CW-F07 Detect distribution shift CW-EP06 CW-C06, CW-F02, CW-F06
CW-F08 Backtest frozen forecast decisions CW-EP06 CW-F05, CW-F06, CW-F07
CW-G01 Define decision prerequisites CW-EP07 CW-C01, CW-B02, CW-B04, CW-B05, CW-B06, CW-N11
CW-G02 Assemble bounded context CW-EP07 CW-G01, CW-C05, CW-C06
CW-G03 Define startup readiness CW-EP07 CW-G01
CW-G04 Separate proposal and verification CW-EP07 CW-G01, CW-N12
CW-G05 Calibrate abstention CW-EP07 CW-G02, CW-F02
CW-G06 Record decision evidence CW-EP07 CW-G02, CW-G03, CW-G04
CW-G07 Handle concurrent decisions CW-EP07 CW-G06, CW-C04
CW-G08 Review learning updates CW-EP07 CW-G06, CW-C06
CW-H01 Freeze hypotheses and metrics CW-EP08 CW-N19
CW-H05 Evaluate strong baselines CW-EP08 CW-H02, CW-H03, CW-H04, CW-G04, CW-F08, CW-E08, CW-D08, CW-C08, CW-N18, CW-N20
CW-H06 Run ablations and uncertainty analysis CW-EP08 CW-H05, CW-G08
CW-N19 Register study protocols and matched baselines CW-EP08 CW-A07, CW-B06, CW-N09, CW-N11
CW-N20 Plan statistical units, power and multiplicity CW-EP08 CW-N19, CW-N16
CW-I01 Reassess novelty CW-EP09 CW-A08, CW-B08, CW-N09
CW-I02 Bind claims to evidence CW-EP09 CW-A07, CW-N10
CW-I03 Prepare canonical manuscripts CW-EP09 CW-I01, CW-I02, CW-N30
CW-I04 Freeze reproducibility packages CW-EP09 CW-I03
CW-I05 Obtain substantive review CW-EP09 CW-I04, CW-N31
CW-I06 Integrate through repository gates CW-EP09 CW-I05
CW-I07 Publish and verify served content CW-EP09 CW-I06
CW-I08 Admit indexing and maintain revisions CW-EP09 CW-I07
CW-N30 Define claim-specific publication release matrix CW-EP09 CW-N02, CW-N09
CW-N31 Maintain trilingual terminology and fidelity CW-EP09 CW-B04, CW-N02
CW-N32 Maintain revisions, negative findings and withdrawal CW-EP09 CW-G08, CW-N10
CW-N11 Specify objectives, tradeoffs and infeasibility CW-EP10 CW-B02, CW-B06
CW-N12 Discharge conditional admissibility obligations CW-EP10 CW-B05, CW-C01, CW-N11
CW-N14 Implement dimensional and availability checks CW-EP10 CW-B05
CW-N15 Bind data access, rights and measurement purposes CW-EP11 CW-N02, CW-N10
CW-N16 Build reference datasets and data dictionaries CW-EP11 CW-C02, CW-C03, CW-C04, CW-N15
CW-N17 Create independent oracles and mutation controls CW-EP12 CW-N12, CW-D01
CW-N18 Validate conceptual and operational simulation models CW-EP12 CW-N16, CW-N17, CW-D03, CW-E03, CW-C01, CW-H02, CW-H03, CW-H04
CW-H02 Build the manufacturing benchmark CW-EP13 CW-D03, CW-D04, CW-D06, CW-H01, CW-N17
CW-H03 Build the service benchmark CW-EP14 CW-E03, CW-C03, CW-H01
CW-H04 Build the project benchmark CW-EP15 CW-C01, CW-C04, CW-H01
CW-E06 Separate performance from causation CW-EP16 CW-B06, CW-C05
CW-F06 Check endogenous observations CW-EP16 CW-C03, CW-C05
CW-N29 Design bounded field intervention CW-EP16 CW-E06, CW-H01, CW-N15, CW-H07
CW-N22 Specify organization decision adapter contracts CW-EP17 CW-G03, CW-G04, CW-G06, CW-C07
CW-N23 Exercise concurrent decision and recovery semantics CW-EP17 CW-G07, CW-N22
CW-N24 Measure scale, latency and total decision cost CW-EP17 CW-N22, CW-H05
CW-N26 Prepare Arcanada collective shadow consumer CW-EP18 CW-G08, CW-N22, CW-N23, CW-H01, CW-N15
CW-N27 Prepare a second eligible organizational shadow consumer CW-EP18 CW-G08, CW-N22, CW-N23, CW-H01, CW-N15
CW-N25 Evaluate decision explanation and human use CW-EP19 CW-G06, CW-N19
CW-H07 Run a shadow evaluation CW-EP20 CW-H06, CW-N26, CW-N24, CW-N25
CW-H08 Evaluate a bounded field intervention CW-EP20 CW-H07, CW-E06, CW-N29
CW-N28 Run held-out transfer and external reproduction CW-EP20 CW-H06, CW-N16
CW-N13 State recursive feasibility and stability conditions CW-EP21 CW-N12, CW-D03, CW-F04
CW-N10 Specify claim and evidence lineage CW-EP22 CW-A01

Scientific series and engineering companions

These are candidate boundaries, not sixteen completed or accepted papers. Final partition follows the research. Each artifact instantiates I03–I08 with its own source, result, review and release evidence.

Candidate Research question Engineering companion Primary work packages
CW-P01 — Research map What is known, and which gap remains testable? Search, screening, corpus, and claim map CW-A01, CW-A02, CW-A03, CW-A04, CW-A05, CW-A06, CW-A07, CW-A08, CW-N09, CW-N10
CW-P02 — Organizational needs How is a gap defined relative to an objective, conditions, and time? Faceted need representation CW-B01, CW-B02, CW-B06, CW-C03, CW-N11
CW-P03 — Networks of work Which dependencies connect tasks and departments? Typed process graph CW-C01, CW-C02, CW-C04, CW-G07, CW-N23
CW-P04 — Resource semantics How can resource types be combined without losing their distinct behavior? Units, inventories, capacity, and availability schemas CW-B05, CW-C04, CW-D01, CW-D04, CW-D06, CW-N12, CW-N14
CW-P05 — Professional capabilities How do occupation, role, task, capability, and evidence relate? Classifier mappings and competency profiles CW-B03, CW-B04, CW-E01, CW-E02, CW-E07, CW-N21
CW-P06 — System performance What constitutes improvement of the overall system? Metrics and local-KPI counterexamples CW-B06, CW-D07, CW-E06, CW-H05, CW-N11, CW-N20
CW-P07 — Flow coordination When should admission be limited or capacity expanded? Queue, buffer, and release experiments CW-D01, CW-D02, CW-D03, CW-D04, CW-D05, CW-D06, CW-D07, CW-D08, CW-H02, CW-N17, CW-N18
CW-P08 — Team composition Which combination and quantity of qualifications are needed? Joint staffing and scheduling models CW-E01, CW-E02, CW-E03, CW-E08, CW-H03, CW-N21
CW-P09 — Capability development How should hiring, training, and automation be compared? Ramp-up, mentoring, and investment models CW-E04, CW-E05, CW-F04, CW-H08, CW-N21, CW-N29
CW-P10 — Environment and forecasts How do external changes affect requirements? Probabilistic forecasts and scenarios CW-F01, CW-F02, CW-F03, CW-F04, CW-F05, CW-F06, CW-F07, CW-F08, CW-N16, CW-N20
CW-P11 — Knowledge sufficiency Which evidence is necessary for a particular decision? Organizational Agent Situation profile CW-C05, CW-C06, CW-C08, CW-G01, CW-G02, CW-G03, CW-G05, CW-N10, CW-N22, CW-N25
CW-P12 — Justified choice How does knowledge support an admissible action? Preconditions, verifier, and decision record CW-F05, CW-G03, CW-G04, CW-G06, CW-G07, CW-N12, CW-N22, CW-N23
CW-P13 — Causal evaluation How can worker, process, and environmental effects be separated? Attribution and intervention protocols CW-E06, CW-F06, CW-H07, CW-H08, CW-N19, CW-N20, CW-N29
CW-P14 — Stable control Under what conditions are overload and harmful oscillation controlled? Conditional results and stress tests CW-D03, CW-D05, CW-F04, CW-F07, CW-H02, CW-H03, CW-H04, CW-N13, CW-N18
CW-P15 — Transfer across organizations Which conclusions remain applicable in a new setting? Held-out organizations and industries CW-B08, CW-H02, CW-H03, CW-H04, CW-H06, CW-H08, CW-N28
CW-P16 — Knowledge revision How should outcomes and counterexamples change the model? Versioned hypotheses, rules, and evidence CW-C06, CW-G08, CW-I02, CW-I08, CW-N10, CW-N32

Per-paper release gates

Coverage mappings are not release permission. Each of the sixteen papers has an explicit claim scope and typed required-evidence edges. The current proposal adds 138 such edges and sixteen release-instance templates containing 96 stage nodes. These are counted separately from the 104 work packages and 247 package dependencies; none is a created native task or accepted result.

Each release instance substitutes its own outputs into I03–I08 and must place every required gate upstream of its manuscript and final release. The validator rejects a P13 release missing H08, an advisory link substituted for an evidence dependency, or another paper’s stage output. Registration preparation includes these contracts in the native scope templates and emits separate release DAG templates; it sends no requests.

P09 and P13 organizational-effect scopes and P15 organizational-transfer scope require H08 plus the causal and intervention prerequisites. Review, model and formal scopes do not acquire a universal H08 dependency. An earlier protocol-only or narrower formal contribution needs a separate reviewed scope contract that excludes unobserved effect claims; it cannot silently weaken one of the contracts below.

External reproduction N28 consumes frozen H06 evaluation inputs and N16 data packages. Before independent execution it pins code, environment, model, configuration and seeds. It does not wait for I04 of the paper whose release it must gate; the final I04 package later includes its receipts.

Paper Declared claim scope Required evidence gates
CW-P01 Reviewed research map with appraised primary sources and explicit unresolved gaps. CW-A01, CW-A02, CW-A03, CW-A04, CW-A05, CW-A06, CW-A07, CW-A08, CW-N09, CW-N10
CW-P02 Representation of organizational needs and obligations; no measured organizational benefit is claimed. CW-B01, CW-B02, CW-B06, CW-C03, CW-N11
CW-P03 Typed work dependencies and concurrent resource semantics under stated assumptions. CW-C01, CW-C02, CW-C04, CW-G07, CW-N23
CW-P04 Resource types, units and conditional admissibility; no unrestricted universal resource law. CW-B05, CW-C04, CW-D01, CW-D04, CW-D06, CW-N12, CW-N14
CW-P05 Task-specific capability, competency evidence and team conditions; occupation titles do not establish individual ability. CW-B03, CW-B04, CW-E01, CW-E02, CW-E07, CW-N21
CW-P06 System performance and local-metric counterexamples in declared validated comparisons, not field effects. CW-B06, CW-D07, CW-E06, CW-H05, CW-N11, CW-N20, CW-H01, CW-N17, CW-N18, CW-H06
CW-P07 Flow and release-policy comparisons within the validated manufacturing model and declared operating region. CW-D01, CW-D02, CW-D03, CW-D04, CW-D05, CW-D06, CW-D07, CW-D08, CW-H02, CW-N17, CW-N18, CW-H01, CW-H05, CW-H06, CW-N20
CW-P08 Qualification-aware staffing and scheduling comparisons in the declared service model. CW-E01, CW-E02, CW-E03, CW-E08, CW-H03, CW-N21, CW-H01, CW-N17, CW-N18, CW-H05, CW-H06, CW-N20
CW-P09 Measured organizational effects of hiring, training or automation under the evaluated bounded intervention. CW-E04, CW-E05, CW-F04, CW-H08, CW-N21, CW-N29, CW-E06, CW-F06
CW-P10 Time-respecting forecast and uncertainty backtests; prediction quality is separate from intervention effects. CW-F01, CW-F02, CW-F03, CW-F04, CW-F05, CW-F06, CW-F07, CW-F08, CW-N16, CW-N20
CW-P11 Organizational knowledge prerequisites and bounded context; effectiveness requires separately scoped comparative evidence. CW-C05, CW-C06, CW-C08, CW-G01, CW-G02, CW-G03, CW-G05, CW-N10, CW-N22, CW-N25
CW-P12 Conditional admissibility and verifiable decision records under explicit assumptions, not unconditional future safety. CW-F05, CW-G03, CW-G04, CW-G06, CW-G07, CW-N12, CW-N22, CW-N23
CW-P13 Causal effects under an identified bounded field design with observed interventions and stated interference limits. CW-E06, CW-F06, CW-H07, CW-H08, CW-N19, CW-N20, CW-N29
CW-P14 Conditional stability results and finite operational criteria within declared models; no universal field guarantee. CW-D03, CW-D05, CW-F04, CW-F07, CW-H02, CW-H03, CW-H04, CW-N13, CW-N18
CW-P15 Held-out cross-organization transfer of observed intervention outcomes with independent reproduction and explicit transport limits. CW-B08, CW-H02, CW-H03, CW-H04, CW-H06, CW-H08, CW-N28, CW-E06, CW-F06, CW-N29
CW-P16 Versioned knowledge revision, contradiction handling and evidence invalidation; no automatic runtime authority. CW-C06, CW-G08, CW-I02, CW-I08, CW-N10, CW-N32

Hypotheses and possible refutation

Each hypothesis maps to H01 preregistration and N20 statistical design plus the domain-specific work packages in the JSON. All outcomes remain unknown.

Hypothesis Comparison What would challenge the claim
CW-HYP01 — 1. The domain profile improves admissibility Strong ordinary RAG versus the profile, with matched information and budgets No reliable improvement, or improvement explained by extra context alone
CW-HYP02 — 2. Cross-process dependencies reduce local harm Local-KPI policy versus a policy using connected-process objectives Overall service, quality, or accepted output worsens under the declared tradeoffs
CW-HYP03 — 3. Knowledge invalidation reduces stale decisions Same profile with and without invalidation Stale-action frequency does not improve; separately assess update cost and false blocks
CW-HYP04 — 4. External verification improves constraint compliance Prompt-only constraints versus an external verifier No compliance improvement, or increased false acceptance/rejection defeats the registered objective
CW-HYP05 — 5. Qualification-aware staffing improves feasibility Joint skill coverage and scheduling versus aggregate workload division Assignments remain infeasible or gains disappear in held-out settings
CW-HYP06 — 6. Explicit action lags improve capacity decisions Instantaneous availability assumption versus hiring, training, and mentoring lags Predicted capacity or service fails to improve after hidden support costs are included
CW-HYP07 — 7. Causal constraints reduce false attribution Cases with identifiable effects and cases with insufficient identification Confident unsupported attribution persists or appropriate abstention fails
CW-HYP08 — 8. Explicit uncertainty improves decision quality Probabilistic or robust decision versus a point estimate No benefit under a predefined quality criterion and accepted conservatism tradeoff
CW-HYP09 — 9. Selective clarification improves utility Clarify selectively versus always act, always ask, and a simple threshold rule Information cost and errors yield no advantage over the simple rule
CW-HYP10 — 10. Model rankings transfer Predicted intervention rankings versus independently observed held-out outcomes Effect direction or decision ranking fails within the stated transfer scope
CW-HYP11 — 11. Control meets a declared stability criterion Loads, delays, and disturbances inside a specified operating region The registered stability or recovery criterion is violated
CW-HYP12 — 12. Evidence supports independent reproduction Repeat using fixed source, data, configuration, and model versions Material differences lack a recorded stochastic or environmental explanation

Execution and evidence gates

Use Muneral registration for scope reconciliation, actual parent/owner binding, idempotent-by-reconciliation creation and exact dependency readback. The offline preparation tool emits templates, never HTTP requests. Partial visibility cannot establish that work is absent.

Keep source/data/code versions, attempts, claims, verdicts and execution events separately identified. Preserve contradictory evidence; validate empty possible-world sets, insufficient authority, unavailable resources and failed/partial effects explicitly. A knowledge packet describing a permission does not grant it. Current task admission, applicable data rights and experiment budgets are checked before use.

Measured costs must include source appraisal, annotation, human review, models/tools, failed attempts and maintenance. Current programme cost and delivery dates are NOT_MEASURED; no empirical experiment is activated by this planning artifact.

Reproduce the proposal checks

python3 -B tools/check_cw_programme.py
python3 -B -m unittest tools.test_check_cw_programme -v
python3 -O -B -m unittest tools.test_check_cw_programme -v
python3 -B tools/render_cw_programme.py --check

The checks validate finite structure, coverage and stated evidence boundaries. They do not certify scientific truth, novelty, review, native registration, deployment or effective use.